    Switch deployment in distribution networks

    , Article Power Systems ; Issue 9789811070006 , 2018 , Pages 179-233 ; 16121287 (ISSN) Izadi, M ; Farajollahi, M ; Safdarian, A ; Sharif University of Technology
    Springer Verlag  2018
    Abstract
    This chapter presents the optimal switch deployment in distribution systems. First, an explanation regarding different types of switches and their functionality is introduced. Then, a fundamental description of fault management procedure in distribution networks is presented. Thereafter, the mathematical formulation of optimal fault management process is described. Optimal switch deployment problem is formulated in the format of mixed integer programming (MIP). The impact of remote controlled switch (RCS) and manual switch (MS) is scrutinized on the interruption cost once they are installed either individually or simultaneously. The concept of switch malfunctions is explained and the... 

    Optimal placement of sectionalizing switch considering switch malfunction probability

    , Article IEEE Transactions on Smart Grid ; Volume 10, Issue 1 , 2019 , Pages 403-413 ; 19493053 (ISSN) Farajollahi, M ; Fotuhi Firuzabad, M ; Safdarian, A ; Sharif University of Technology
    Institute of Electrical and Electronics Engineers Inc  2019
    Abstract
    Sectionalizing switches (SSs) are often presumed to function fully reliable. However, SSs are exposed to have some malfunctions, whereby undermining their ability to improve service reliability. This paper presents a model to integrate SS malfunction probability into SS placement problem. The model aims to minimize the total SSs costs as well as customers interruption cost. The proposed model is formulated in mixed integer programing, which can be easily solved via several available solvers and gain global optimal solution. The proposed model indicates the extent to which the placement problem is affected by uncertainty associated with SSs functionality, and how not considering SSs... 

    Optimal placement of sectionalizing switch considering switch malfunction probability

    , Article IEEE Transactions on Smart Grid ; Volume 10, Issue 1 , 2019 , Pages 403-413 ; 19493053 (ISSN) Farajollahi, M ; Fotuhi Firuzabad, M ; Safdarian, A ; Sharif University of Technology
    Institute of Electrical and Electronics Engineers Inc  2019
    Abstract
    Sectionalizing switches (SSs) are often presumed to function fully reliable. However, SSs are exposed to have some malfunctions, whereby undermining their ability to improve service reliability. This paper presents a model to integrate SS malfunction probability into SS placement problem. The model aims to minimize the total SSs costs as well as customers interruption cost. The proposed model is formulated in mixed integer programing, which can be easily solved via several available solvers and gain global optimal solution. The proposed model indicates the extent to which the placement problem is affected by uncertainty associated with SSs functionality, and how not considering SSs... 

    Reliability Oriented Optimal Placement of Sectionalizing Switches and Fault Indicators

    , M.Sc. Thesis Sharif University of Technology Farajollahi, Mohammad (Author) ; Fotuhi-Firuzabad, Mahmud (Supervisor) ; Safdarian, Amir (Co-Advisor)
    Abstract
    Nowadays, electricity has a substantial impact on various aspects of peoples’ life, which has captured the attention of electricity planners and operators. However, despite the expectation of customers to have access to an uninterrupted electricity, multitude of technical and economical challenges prevent to achieve fully reliable power supply. Due to especial structure of distribution systems and limited investment budgets, distribution systems play a critical role in delivering electricity to the customers. According to past statistical information, up to 80 percent of electricity outage originates from failure of distribution equipment or the matters relevant to distribution level.... 

    Impacts of remote control switch malfunction on distribution system reliability

    , Article IEEE Transactions on Power Systems ; Volume 32, Issue 2 , 2017 , Pages 1572-1573 ; 08858950 (ISSN) Safdarian, A ; Farajollahi, M ; Fotuhi Firuzabad, M ; Sharif University of Technology
    Institute of Electrical and Electronics Engineers Inc  2017
    Abstract
    Remote control switches (RCSs) are often assumed to be fully reliable in reliability and cost/worth analyses. This assumption, however, overestimates their merits, thereby misguiding network owners about their optimal implementation. This letter extends the current reliability evaluation procedure to incorporate probability of RCS malfunctions. Then, the extended procedure is applied to a network equipped with a few RCSs. The numerical studies reveal that RCS malfunctions degrade their worth, which may even affect their optimal number and locations. © 1969-2012 IEEE  

    A MIP model for risk constrained switch placement in distribution networks

    , Article IEEE Transactions on Smart Grid ; 2018 ; 19493053 (ISSN) Izadi, M ; Safdarian, A ; Sharif University of Technology
    Institute of Electrical and Electronics Engineers Inc  2018
    Abstract
    The great share of interruptions in distribution networks motivates distribution decision makers to establish various reliability enhancement strategies. Amongst, deploying remote controlled switch (RCS) can make a crucial contribution to the reduction of interruption costs. Nevertheless, the stochastic nature of contingencies affects the RCS worth and imposes substantial financial risk to RCS deployment projects. This paper proposes a mathematical model to consider the risk in the optimal RCS deployment problem. The model determines the number and location of RCSs such that the expected profit is maximized while financial risk is minimized. The risk is modeled through conditional... 

    Simultaneous placement of fault indicator and sectionalizing switch in distribution networks

    , Article IEEE Transactions on Smart Grid ; 2018 ; 19493053 (ISSN) Farajollahi, M ; Fotuhi Firuzabad, M ; Safdarian, A ; Sharif University of Technology
    Institute of Electrical and Electronics Engineers Inc  2018
    Abstract
    Automation systems provide substantial improvement in service reliability through speeding up fault management procedure. However, this is at expense of high investments whose justification needs thorough cost/worth analyses. This paper introduces a mathematical model to optimally place automation system devices within distribution networks. The model establishes a trade-off between service reliability improvements and the relevant costs. Among different automation system devices, fault indicators and remote controlled switches are considered here. Also, the impact of manual switches is regarded since their number and location significantly affect the solution of the placement problem. The... 

    Financial risk evaluation of RCS deployment in distribution systems

    , Article IEEE Systems Journal ; 2018 ; 19328184 (ISSN) Izadi, M ; Safdarian, A ; Sharif University of Technology
    Institute of Electrical and Electronics Engineers Inc  2018
    Abstract
    Remote controlled switch deployment in distribution networks is usually justified via comparing the required investment with the expected decrease in interruption costs. Although the investment is known prior to the implementation, the stochastic nature of contingencies imposes significant uncertainty on interruption costs. The uncertainty may impose substantial financial risks on the distribution company. This paper aims at evaluating the financial risk and key affecting parameters. For doing so, a step-by-step method is presented to evaluate the risk. The method captures the stochastic nature of contingencies through a sequential Monte Carlo simulation approach. A mathematical formulation... 

    A MIP model for risk constrained switch placement in distribution networks

    , Article IEEE Transactions on Smart Grid ; Volume 10, Issue 4 , 2019 , Pages 4543-4553 ; 19493053 (ISSN) Izadi, M ; Safdarian, A ; Sharif University of Technology
    Institute of Electrical and Electronics Engineers Inc  2019
    Abstract
    The great share of interruptions in distribution networks motivates distribution decision makers to establish various reliability enhancement strategies. Amongst these strategies, deploying remote controlled switch (RCS) can make a crucial contribution to the reduction of interruption costs. Nevertheless, the stochastic nature of contingencies affects RCS worth and imposes substantial financial risk to RCS deployment projects. This paper proposes a mathematical model to consider the risk in the optimal RCS deployment problem. The model determines the number and location of RCSs such that the expected profit is maximized while financial risk is minimized. The risk is modeled through... 

    Simultaneous placement of fault indicator and sectionalizing switch in distribution networks

    , Article IEEE Transactions on Smart Grid ; Volume 10, Issue 2 , 2019 , Pages 2278-2287 ; 19493053 (ISSN) Farajollahi, M ; Fotuhi Firuzabad, M ; Safdarian, A ; Sharif University of Technology
    Institute of Electrical and Electronics Engineers Inc  2019
    Abstract
    Automation systems provide substantial improvement in service reliability through speeding up fault management procedure. However, this is at expense of high investments whose justification needs thorough cost/worth analyses. This paper introduces a mathematical model to optimally place automation system devices within distribution networks. The model establishes a trade-off between service reliability improvements and the relevant costs. Among different automation system devices, fault indicators and remote controlled switches are considered here. Also, the impact of manual switches is regarded since their number and location significantly affect the solution of the placement problem. The... 

    Financial risk evaluation of RCS deployment in distribution systems

    , Article IEEE Systems Journal ; Volume 13, Issue 1 , 2019 , Pages 692-701 ; 19328184 (ISSN) Izadi, M ; Safdarian, A ; Sharif University of Technology
    Institute of Electrical and Electronics Engineers Inc  2019
    Abstract
    Remote controlled switch deployment in distribution networks is usually justified via comparing the required investment with the expected decrease in interruption costs. Although the investment is known prior to the implementation, the stochastic nature of contingencies imposes significant uncertainty on interruption costs. The uncertainty may impose substantial financial risks on the distribution company. This paper aims at evaluating the financial risk and key affecting parameters. For doing so, a step-by-step method is presented to evaluate the risk. The method captures the stochastic nature of contingencies through a sequential Monte Carlo simulation approach. A mathematical formulation... 

    An Milp model for switch, DG, and tie line placement to improve distribution grid reliability

    , Article IEEE Systems Journal ; 2022 , Pages 1-12 ; 19328184 (ISSN) Zare Bahramabadi, M ; Ehsan, M ; Farzin, H ; Sharif University of Technology
    Institute of Electrical and Electronics Engineers Inc  2022
    Abstract
    Remote controlled switches (RCSs) have the ability to isolate the faulted area from other parts of the distribution system. On the other hand, the dispatchable distributed generators (DDGs) and tie lines can supply the interrupted loads after fault occurrence trough microgrids and reduce the outage time. In this regard, this article proposes a planning model for simultaneous placement of RCSs, DDGs, and tie lines to improve distribution system reliability. The presence of renewable distributed generations (RDGs) and energy storage systems, which have an increasing penetration in today's distribution networks are also considered. Moreover, two different practical load shedding methods are... 

    Optimal Placement of Remote Control Switches to Reduce Network Losses and Enhance Service Quality

    , M.Sc. Thesis Sharif University of Technology Gharebaghi, Sina (Author) ; Safdarian, Amir (Supervisor)
    Abstract
    Nowadays, improvement in operational condition of distribution networks considering daily growth in electrical energy usage with financial limits appears as a huge challenge for network operators. Under these kind of circumstances, operators need to have efficient and inexpensive plans more than ever. Considering high share of power losses in overall pro-duced power, utilities always tried to minimize losses in Iran and other points of world. In addition, numerous equipment in distribution networks compared with the transmission level, impose high costs to reliability plans. Therefore, reliability improvement plans have been paid low attention by distribution network operators. This lower... 

    Fault Management in Power Distribution Systems Manual & Remote Switchings Timing and Repair Crew Scheduling

    , M.Sc. Thesis Sharif University of Technology Jalilian, Ali (Author) ; Safdarian, Amir (Supervisor)
    Abstract
    Prompt service restoration following faults has always been a concern to power distribution utilities. In this regard, optimal human resource allocation in post-fault service restoration can speed up field remedial actions which count for significant portion of service interruption duration. This thesis develops a fault management navigator that dispatches crews for field actions in a sequential service restoration until the network is restored to the normal state. The developed navigator effectively coordinates manual and remote switching actions as well as repair actions in the hope of achieving minimum service interruption cost. It tackles a real-time problem, periodically updating the... 

    Optimal placement of sectionalizing switch considering switch malfunction probability

    , Article IEEE Transactions on Smart Grid ; 2017 ; 19493053 (ISSN) Farajollahi, M ; Fotuhi Firuzabad, M ; Safdarian, A ; Sharif University of Technology
    Abstract
    Sectionalizing switches (SSs) are often presumed to function fully reliable. However, SSs are exposed to have some malfunctions, whereby undermining their ability to improve service reliability. This study presents a model to integrate SS malfunction probability into SS placement problem. The model aims to minimize the total SSs costs as well as customers interruption cost. The proposed model is formulated in mixed integer programing (MIP), which can be easily solved via several available solvers and gain global optimal solution. The proposed model indicates the extent to which the placement problem is affected by uncertainty associated with SSs functionality, and how not considering SSs... 

    Financial risk constrained remote controlled switch deployment in distribution networks

    , Article IET Generation, Transmission and Distribution ; Volume 12, Issue 7 , 2018 , Pages 1547-1553 ; 17518687 (ISSN) Izadi, M ; Safdarian, A ; Sharif University of Technology
    Institution of Engineering and Technology  2018
    Abstract
    Recently, diverse technologies and apparatus are launched to enhance service reliability in the distribution level. In this regard, remote controlled switches (RCSs) can play a prominent role in declining interruption durations and costs. The stochastic nature of contingencies, however, imposes considerable uncertainty on the achievements of RCS deployment. This study presents a model to consider the financial risk induced by the uncertainty in an RCS placement problem. The risk awareness of distribution companies is scrutinised through an effective risk measure, i.e. conditional value at risk. In the model, the number and location of RCSs are determined such that the system expected cost is... 

    Effect of sectionalizing switches malfunction probability on optimal switches placement in distribution networks

    , Article International Journal of Electrical Power and Energy Systems ; Volume 119 , July , 2020 Khani, M ; Safdarian, A ; Sharif University of Technology
    Elsevier Ltd  2020
    Abstract
    Sectionalizing switches (SSs) are installed in distribution networks to provide ring and maneuver points, thereby increasing service reliability. These switches are either manual switches (MSs) or remote controlled switches (RCSs). The switches are usually assumed to be fully reliable. However, in practice, their performance is not always ideal. Actually, the switches may sometimes experience malfunction, which reduces their ability to enhance system reliability. The present study proposes a model to consider the malfunction possibility of the switches in their optimal placement problem. The model helps to minimize the total costs of SSs as well as the interruption costs incurred by... 

    A reliability cost/worth approach to determine optimum switching placement in distribution systems

    , Article 2005 IEEE/PES Transmission and DistributionConference and Exhibition - Asia and Pacific, Dalian, 15 August 2005 through 18 August 2005 ; Volume 2005 , 2005 , Pages 1-5 ; 0780391144 (ISBN); 9780780391147 (ISBN) Moradi, A ; Fotuhi Firuzabad, M ; Rashidi Nejad, M ; Sharif University of Technology
    2005
    Abstract
    Nowadays automation in distribution systems is growing largely. Automated and remote controlled switches play prominent rules in automated distribution systems. By opening and closing these remote controlled switches in emergency states when a fault has been occurred we can manage fault and restoration process in order to minimize interruption time and costs. In the normal states feeder load management and power loss minimization can be controlled by these remote controlled switches. Finding optimum numbers and optimum locations for installing these switches is the main concern in this between. Up to now a number of algorithms have been developed for optimum switch placement. In this paper a... 

    Electrical Distribution System Planning in Multi-Microgrid Framework

    , M.Sc. Thesis Sharif University of Technology Zare Bahramabadi, Majid (Author) ; Ehsan, Mehdi (Supervisor) ; Farzin, Hossein (Co-Supervisor)
    Abstract
    Remote-controlled switches (RCSs) have the ability to quickly isolate the faulted area from other parts of distribution systems. On the other hand, the distributed generation resources (DGs) and tie lines can supply the interrupted loads after fault occurrence as a microgrid. In this regard, this thesis proposes a planning model for simultaneous placement of RCSs, DGs, and tie lines in distribution systems with complex topologies to improve their reliability and resiliency. Presence of renewable DGs (RDGs) including photovoltaic cells (PVs) and wind turbines (WTs), as well as the uncertainties of loads, RDGs, and outage duration of the faulted areas are also considered in the proposed... 

    A multistage MILP-based model for integration of remote control switch into distribution networks

    , Article 2016 International Conference on Probabilistic Methods Applied to Power Systems, PMAPS 2016 - Proceedings, 16 October 2016 through 20 October 2016 ; 2016 ; 9781509019700 (ISBN) Izadi, M ; Farajollahi, M ; Safdarian, A ; Fotuhi Firuzabad, M ; Sharif University of Technology
    Institute of Electrical and Electronics Engineers Inc  2016
    Abstract
    In the past decades, remote control switches have been broadly integrated into distribution systems to achieve a certain level of service reliability. To take utmost benefits of them, a cost-benefit analysis should be conducted. In this regard, the budget restriction plays a crucial role in remote control switch placement. This paper is aimed at proposing a model to determine the optimal number and location of remote control switches in a distribution system. As the main contribution of the paper, the model is developed in multistage planning format to address the issue of budget limitation. To this end, the model is formulated in mixed integer linear programming format, which tries to...